4125 system sent to Turkmenistan;
Date shipped from warehouse 8 Feb 2012
Date shipped from Baku 14 Mar 2012
Date of arrival into Teesside 12 April 2012

KJ – sailed for Ghana 15 Mar 2012
Alongside Takoradi 8 Apr 2012
Vessel currently on standby for a project start up around the 14th May.

Aquarius – 12006GPH
Mob start date 17 Apr 2012
End date 21 Apr 2012
Equipment in use – sparker, Edgetech 4200, pinger, R2Sonics

Albatross1 – 11525GPH
Mob start date 27 Mar 2012 – then 4 weeks alongside on standby due to on-going permit, visa, and kit stuck in customs issues. –
will you allow us some leeway to account for the time spent alongside due to issues in the main out of our control.
22 Apr 2012 Vessel sailed for site after equipment hand carried to vessel owing to on-going issues of equipment in customs.
Due to complete 11 May 2012
Equipment in use;
Amplicon, C-Max towfish, towed sparker, 1×2 pinger

Invoices:
MG3 March:
MG3-001: £18,482.99
MG3-002: £23,878.93
MG3-003: £23,878.93
MG3 April:
MG3-004: £59,657.60

14 Apr WEATHER – 17 Apr -21 Apr